The Problem
An auto dealership needed 12 Level 2 EV chargers across their lot within a tight 5-day window before a manufacturer audit.
Our Solution
Panel upgrade to 400A service, trenching, conduit installation, and 12 smart charger deployments with fleet management software integration.
Project Timeline
- 1
Assessment
Site survey, load calculation, and permit research completed within 24 hours.
- 2
Planning
Detailed scope document and fixed-price quote issued and approved by client.
- 3
Installation
Licensed crew on site. All work performed to NEC code with daily progress updates.
- 4
Inspection
Authority-having-jurisdiction (AHJ) inspection passed first time.
- 5
Handover
System test with client. Documentation and warranty issued.
Materials & Standards
- Copper conductors (NEC compliant)
- Listed breaker panels and breakers
- AFCI/GFCI devices as required
- Conduit and fittings
- Approved junction boxes and covers
Outcome
Passed manufacturer audit. Dealership reports $8,000/month savings vs. outsourced charging.
Related Services
EV Charger Installation
Level 2 and DC fast charger installation for residential garages and commercial lots.
Commercial Electrical
Full commercial electrical services — tenant fit-outs, lighting design, power distribution.